E.ON Karlshamn EO2 controls upgrade
15 Feb 2011
Karlshamn gas turbine hall

The TCL control system at Karlshamn Power Station has been installed and has successfully completed the site commissioning tests. These tests included rigorous SVK grid compliance testing including:

  • Full load 35MW load rejections.
  • Island load tests.
  • Load acceptance tests.
  • Linear droop tests.
  • Frequency response tests
  • Black start tests
  • Loading rate tests

The grid compliance tests showed that the newly installed TCL system was able to control the plant within the onerous requirements of this power plant. This included fast start-up and full load rejection.